The clean room purification project does not use wood materials and other materials that do not meet the requirements of clean standards.
洁净室内净化工程不使用木质材料和其它不符合洁净标准要求材料。
All approach materials are stored in a clean and dry environment with enclosures.
各种进场材料存放在有围护设施、清洁干燥的环境中。
The thickness, size and quality of the color steel plate must meet the design requirements or contract requirements, and there is a factory inspection report, the production of color steel plate must be carried out in accordance with the secondary design of the panel drawing and the size and quantity list, the production process according to the drawing number, the length of the ceiling plate should not exceed 5000㎜.
彩钢板的厚度、规格尺寸、质量必须符合设计要求或合同要求,并有出厂检验报告,彩钢板的生产必须依照二次设计的拼板图和尺寸数量清单进行,生产过程中按图纸编号,吊顶板的长度不宜超过5000㎜.
Auxiliary materials such as hardware standard parts, must meet the design requirements or contract requirements, there is a factory certificate.
辅助材料如小五金标准件、必须符合设计要求或合同要求,有出厂合格证。
The material and specifications of the section steel for connection should meet the design requirements, and there is a warranty or inspection report, and low carbon steel should be used.
连接用型钢的材质、规格应符合设计要求,有质保书或检验报告,宜采用低碳钢。
The material and specifications of aluminum alloy profiles should meet the design requirements or contract requirements, and there is a factory certificate.
铝合金型材的材质、规格应符合设计要求或合同要求,有出厂合格证。
There are sufficient temporary storage sites for materials and storage sites for aluminum alloy processing and semi-finished products.
有足够的材料临时存放场地和铝合金加工和半成品存放场地。